Quick Response and Delivery in Both Zeeland and France
In both Zeeland and France, we installed machines for TOP The Onion Group to help them overcome temporary energy shortages.
In Zeeland, they are waiting for a major grid upgrade. At the moment, they have a 3-megawatt connection, but will have to wait until next year for a direct 20-megawatt connection. Of course, that doesn’t stop their operations.
With two generators that automatically start up and scale down via their EMS whenever there’s a peak in energy consumption, they can keep running smoothly. The generators step in as soon as the grid supply falls short. Since the energy demand here is both high and long-lasting, a battery system alone would not be sufficient.
In France, they faced different challenges. Their existing generator was malfunctioning, so at their request we urgently delivered a 500 kVA generator. As quickly as possible, we transported the generator — including cables — to the site and installed it. This is how we work at Voet: short lines, fast action, and reliable solutions.
Whether in Zeeland or France, we make sure the energy keeps flowing.